Sustainable Campus Partial Renovation Project (Stage 2)



In addition to reducing or even halting energy use to alleviate the greenhouse effect, we can also replace high-carbon energy sources with low-carbon or carbon-free ones. For this purpose, our school has set up a central utility room for water filtering and recycling and developed a plan to improve the wiring of classroom light fixture switches and the sunshade structure.



Contract price: NT$960,000



Major steps:



    1. Setting up a central utility room for water filtering and recycling



    2. Rewiring classroom light fixture switches



    3. Improving the exterior shade structure